You have been asked to determine a rough schedule for a nine-month Billing System Conversion project, as

Question:

You have been asked to determine a rough schedule for a nine-month Billing System Conversion project, as part of your job as a consultant to a Fortune 500 firm. The firm's old system was written in COBOL on a mainframe computer, and the maintenance costs are prohibitive. The new system win run on an off-the-shelf application. You have identified several high-level activities that must be done in order to initiate, plan, execute, control, and close the project. Table 6-4 shows your analysis of the project's tasks and schedule solar.


You have been asked to determine a rough schedule for


a. Using the information in Table 6-4, draw horizontal bars to illustrate when you think each task would logically start and end. Then use Project 2007 to create a Gantt chart and network diagram based on this information.
b. Identify at least two milestones that could be included under each of the process groups in Table 6-4. Then write a detailed description of each of these milestones that meets the SMARTcriteria.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: