Question: 1. Generate a priority matrix for AETs system move. 2. Develop a WBS for Brians project. Include duration (days) and predecessors. 3. Using a project
1. Generate a priority matrix for AET’s system move.
2. Develop a WBS for Brian’s project. Include duration (days) and predecessors.
3. Using a project planning tool, generate a network diagram for this project. (Base your plan on the following guidelines: eight-hour days, seven-day weeks, no holiday breaks, March 1, 2010, is the project start date.)
Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the “application service provider” world. Their large data center provides clients with remote access to AET’s complete suite of application software systems. Traditionally, one of AET’s primary competitive advantages has been the company’s trademark IT reliability. Due to the complexity of this project, Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.
Step by Step Solution
3.45 Rating (158 Votes )
There are 3 Steps involved in it
1 Priority Matrix TIME PERFORMANCE COST Constrain X Enhance X Accept X 2 3 The size of the network p... View full answer