Using the MS project 2019, develop a WBS for AET. include duration in days and predecessors. Advantage
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Advantage Energy Technology Data Center Migration Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago AET jumped into the "application service provider" world. Their large data center provides clients with remote access to AET's complete suite of application software systems. Traditionally, one of AET's primary competitive advantages have been the company's trademark IT reliability. Due to the complexity of this project, Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised. Currently AET's data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the vice president of operations, Dan Whitmore, with the following guidelines: From start to finish, it is anticipated the entire project will take three to four months to complete. . It is essential that AET's 235 clients suffer no downtime. . Whit more advises Brian to come back to the Executive Committee on February 15 with a presentation on the scope of the project that includes costs, "first-cut" timeline, and proposed project team members. Brian had some preliminary discussions with some of AET's managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from Operations, Systems, Facilities, and Applications. The scope team determined the following: Three to four months is a feasible project timeline, and first-cut cost estimate is $80,000- $90,000 (this includes the infrastructure upgrade of the new site). • Critical to the "no-downtime" requirement is the need to completely rely on AET's remote disaster recovery "hot" site for full functionality. Brian will serve as project manager of a team consisting of one team member each from Facilities, Operations/Systems, Operations/Telecommunications, Systems and Applications, and Customer Service. . . Brian's Executive Committee report was positively received and, after a few modification and recommendations, he was formally charged with responsibility for the project. Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project- planning process. Advantage Energy Technology Data Center Migration Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data center to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago AET jumped into the "application service provider" world. Their large data center provides clients with remote access to AET's complete suite of application software systems. Traditionally, one of AET's primary competitive advantages have been the company's trademark IT reliability. Due to the complexity of this project, Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised. Currently AET's data center is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the vice president of operations, Dan Whitmore, with the following guidelines: From start to finish, it is anticipated the entire project will take three to four months to complete. . It is essential that AET's 235 clients suffer no downtime. . Whit more advises Brian to come back to the Executive Committee on February 15 with a presentation on the scope of the project that includes costs, "first-cut" timeline, and proposed project team members. Brian had some preliminary discussions with some of AET's managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from Operations, Systems, Facilities, and Applications. The scope team determined the following: Three to four months is a feasible project timeline, and first-cut cost estimate is $80,000- $90,000 (this includes the infrastructure upgrade of the new site). • Critical to the "no-downtime" requirement is the need to completely rely on AET's remote disaster recovery "hot" site for full functionality. Brian will serve as project manager of a team consisting of one team member each from Facilities, Operations/Systems, Operations/Telecommunications, Systems and Applications, and Customer Service. . . Brian's Executive Committee report was positively received and, after a few modification and recommendations, he was formally charged with responsibility for the project. Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project- planning process.
Expert Answer:
Answer rating: 100% (QA)
Answers Generate a priority matrix for AETs system move Priority Matrix ConstrainX Enhance Accept 1 ... View the full answer
Related Book For
Project management the managerial process
ISBN: 978-0073403342
5th edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date:
Students also viewed these general management questions
-
A network consists of the following list. Times are given in weeks. Duration Preceding Activity A 9. -- A C A 12 D A E 6. F 8 G , F 3 H D I H 8. G, I , J J 6. K 2 a) Draw the network diagram. Find...
-
1. Generate a priority matrix for AETs system move. 2. Develop a WBS for Brians project. Include duration (days) and predecessors. 3. Using a project planning tool, generate a network diagram for...
-
Given the project within the table below calculate a. The critical path b. The minimum project duration c. The amount of slack for each activity Activity Duration (hours) Immediate Predecessors A 4...
-
The compound bow in the previous problem requires 152 J of work to draw the string back to x = 0.540 m, at which point the archer need only exert 250 N of force to hold the string in place. (a)...
-
A new Corvette weighs 3,273 lb. A manufacturer's scale that is accurate to the nearest 10 lb gives the weight as 3,250 lb, while the U.S. Department of Transportation uses a scale that is accurate to...
-
In Section 11.4.3, we discussed an efficient scheme for sampling a bandpass continuous-time signal with Fourier transform such that? S c (j?) = 0? ? ? ??for |?| ? ? c and |?| ? ? c + ??. In that...
-
Product quality is of paramount importance in chemical product design. Explore the following quality improvement methodologies on the Internet: (a) Fishbone diagram (b) Pareto analysis (c) Process...
-
Your firm has just lost its accounting system. The only thing you have left is the financial reports from the December 31, 20XA and June 30, 20XB reporting period, but the data is garbled. You have...
-
The aviation industry is highly competitive and, to get noticed, you must differentiate yourself. For this reason, the Aviation School designed a flight attendant course, in which knowledge will be...
-
Defend the significance of LG considering the opinions of an executive jury when formulating the business's inventory management policy.
-
Beyer Company is considering buying an asset for $360,000. It is expected to produce the following net cash flows. Year 1 Year 5 $80,000 $13,000 Net cash flows Year 2 $50,000 Year 3 $70,000 Year 4...
-
Provide an alternate perspective on the advantages of using SWOTT over SWOT analysis. Identify an additional aspect of the environmental analysis not covered by SWOTT that would be important to...
-
The graph of y = f(x) is shown below. What are all of the real solutions of f(x) = o? 2 -10 14 4 9 8 10
-
2. Kofi is interested in the effect of the introduction of the Free Senior High School (Free -SHS) in the Ghana on the unemployment rate (Number of unemployed/ Labour force) and applies a...
-
Find the page in the slides, with the code below and the corresponding memory drawing. How many boxes are drawn and what is the total memory used (the sum of the sizes of those boxes)? struct node *...
-
Discuss the key advantages and disadvantages of the various payment methodologies for hospitals from the point of view of a managed care plan, by type of plan. Perform the same exercise, but from the...
-
Your company has been contracted to manage the construction of a new apartment complex. The project has a tight budget and timeline, and the client is concerned about the project being completed on...
-
Before the latest financial crisis and recession, when was the largest recession of the past 50 years, and what was the cumulative loss in output over the course of the slowdown?
-
It is possible to shorten the critical path and save money. Explain how.
-
Why is a conductor of an orchestra an appropriate metaphor for being a project manager? What aspects of project managing are not reflected by this metaphor? Can you think of other metaphors that...
-
Given the time-phased work packages and network, complete the baseline budget form for theproject. Soccer Toy Project & test Legend ESID | EF SL Description LS | DURI LF Soccer Toy Project Cost by...
-
Consider the multiple linear regression model fit to the baseball data in Problem 3.41. Problem 3.41 Consider the 2016 major league baseball data in Table B.22. While team ERA was useful in...
-
Consider the simple linear regression model fit to the rental price data from Problem 2.36. Data From Problem 2.36 Table B.24 contains data on median family home rental price and other data for 51 US...
-
Consider the multiple linear regression model fit to the rental price data in Problem 3.42. Problem 3.42 Table B.24 contains data on median family home rental price and other data for 51 US cities....
Study smarter with the SolutionInn App