1. Is Doug's Dens a business that can effectively utilize MRP for planning its inventory? Why or...

Question:

1. Is Doug's Dens a business that can effectively utilize MRP for planning its inventory? Why or why not?
2. Develop a material requirements plan for the next 8 weeks using the information in Tables 7.25 and 7.26, and Figure 7.18.
In table 7.25 Master Schedule
1. Is Doug's Dens a business that can effectively utilize

In Table 7.26Current Ordering Policy for Doug's Dens
Part/SubassemblyOrder Quantity/Reorder Point
Corner brackets ......................................Q= 1,000; R = 500
6-foot 2x4 .............................................Q = 4,000; R= 1,000
2-inch nails ...........................................Q= 10,000; R = 1,000

1. Is Doug's Dens a business that can effectively utilize

3. Discuss how Doug should go about implementing MRP. What type of training should he provide? What kind of software and equipment? How long should he allow for the implementation?
4. A business consultant suggested that Doug's Dens build a master schedule at the subassembly level (i.e., for the floor, roof, and frame assemblies) rather than at the finished product level (i.e., Fido's Favorite and Charlie's Castle). The consultant said that this is the approach used by Dell (Doug idolizes Michael Dell as a role model). Discuss whether this approach makes sense and explain why or why not.