Question: A city has developed a plan to provide for future municipal water needs. The plan proposes an aqueduct that passes through 500 feet of tunnel
The friction losses in the half-capacity tunnel will be greater than if the full-capacity tunnel were built. The estimated additional pumping costs in the single half-capacity tunnel will be $2000 per year, and for the two half-capacity tunnels it will be $4000 per year. Based on capitalized cost and a 7% interest rate, which alternative should be selected?
Step by Step Solution
3.55 Rating (155 Votes )
There are 3 Steps involved in it
Full Capacity Tunnel Capitalized Cost 556000 40000 AF 7 10007 556000 40000 00724007 597400 First Ha... View full answer