Question: a. Draw the AOA diagram. b. Find the critical path. c. Find the completion time. Activity TE AB .....1 AC .....2 AD .....3 DC
a. Draw the AOA diagram.
b. Find the critical path.
c. Find the completion time.
Activity †TE
AB .....1
AC .....2
AD .....3
DC .....4
CB .....3
DE .....8
CF .....2
BF .....4
IJ .......2
CE .....6
EF .....5
FG .......10
FH .......11
EH .....1
GH .....9
EJ .....3
GI .....8
HJ.....6
.png)
mes Optimistic Most Likely Pesimistic Preceding Tasks 1 Lay foundation 2 Dig hole for scale 3 Insert scale bases 4 Erect frame 5 Complete building 6 nsert scales 7 Insert display cases 8 Put in office equipment 9 Finishing touches 10 13 21 30 13 10 15 12 20 4 10