Question: Find (a) The AOA network and the critical path. (b) All event slacks. (c) Critical path to event D. (d) Critical path probability of completion
(a) The AOA network and the critical path.
(b) All event slacks.
(c) Critical path to event D.
(d) Critical path probability of completion in 14 days.
(e) The effect if CD slips to 6 days; to 7 days; to 8days.
.png)
b-9763868017 m-6433205414 a-3103202411 EDEFE
Step by Step Solution
3.27 Rating (168 Votes )
There are 3 Steps involved in it
a The critical path is AC CB BE EF b The only event with slack is D at 3 days c If D were t... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
84-B-M-L-P-M (449).docx
120 KBs Word File
