Question: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of four units. The department uses a working

A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of four units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules:

a. In order of most following tasks. Tiebreaker: greatest positional weight.

b. In order of greatest positional weight. Tiebreaker: most following tasks.

c. What is the efficiency?

A manager wants to assign tasks to workstations as efficiently

2b

Step by Step Solution

3.41 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Given Desired output rate 4 units per hour Operating time 56 minutes per hour We are given the tasks and their times in minutes shown below a Use the most following tasks heuristic and in the case of ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

372-B-M-L-O-M (3050).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!