Question: A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The department uses a working time

A manager wants to assign tasks to workstations in order to achieve an hourly output rate of four units. The department uses a working time of 56 minutes per hour.
a. Assign the tasks shown in the following precedence network (times are on the nodes and are in minutes) to workstations using the following heuristic rules: (i) €œAssign the task with the most followers.€ (ii) Tiebreaker: €œAssign the task with the longest time.€ If a tie still exists, choose randomly.
b. What is the efficiency?

A manager wants to assign tasks to workstations in order

8 4 2 5

Step by Step Solution

3.40 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Desired output 4 units per hour Operating time 56 ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

686-B-M-L-O-M (4791).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!