Question: A project consists of five activities- A, B, C, D, and E. Times for each of these activities is uncertain, and the minimum and maximum

"A project consists of five activities- A, B, C, D, and E. Times for each of these activities is uncertain, and the minimum and maximum times are known (Shown in the table below), and any intermediate value is equally probable.
Activity, Immediate Predecessor(s), Minimum time(Days). Maximum Time(days)
A, -- ,1 ,7
B, A ,10 ,18
C, A ,8 ,20
D, B,C ,4 ,6
E, D ,2 ,10

We are interested in finding out the following: 1) the average time it can take to complete the project, and 2) criticality index for activity C. Use excel to mimic or simulate the project 30 times to determine your answer. The term “criticality index” for an activity refers to the probability that the activity is on the critical path. (For ease of analysis, just assume that the time is measured only in rounded number of days. Use –rand between (). Set up a table to list activity times, path lengths, project duration and if activity C is on the critical path. The table would have 30 rows to mimic the project 30 times.

Step by Step Solution

3.38 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

The network diagram for the project is 1 Average time it takes to complete the project average of si... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Excel file Icon

1368-B-M-A-V-C(1572).xlsx

300 KBs Excel File

Students Have Also Explored These Related Managerial Accounting Questions!