Question: A school cafeteria is operated by five persons performing the activities in the aver-age times shown in the following chart. a. What are the bottleneck

A school cafeteria is operated by five persons performing the activities in the aver-age times shown in the following chart.

Activity 1. Serve salad and dessert 2. Pour drinks 3. Serve entre


a. What are the bottleneck activity and the maximum service capacity per hour?

b. Suggest a reallocation of activities that would increase capacity and use only four employees, and draw a product flow diagram. What is the capacity of your improved system?

c. Recommend a way to maintain the serving capacity found in part b using only three employees.

Activity 1. Serve salad and dessert 2. Pour drinks 3. Serve entre 4. Serve vegetables 5. Tally and collect payment Average Time, Sec. 10 30 60 20 40

Step by Step Solution

3.49 Rating (176 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a School Cafeteria Bottleneck is Activity 3 Serve entre ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

517-B-M-L-O-M (3843).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!