Question: A small software development project has four major activities. The times are estimated and provided in the table below: Activity Immediate Predecessor a m b
A small software development project has four major activities. The times are estimated and provided in the table below:
| Activity | Immediate Predecessor | a | m | b |
| A | -- | 2 | 5 | 8 |
| B | A | 3 | 6 | 9 |
| C | A | 4 | 7 | 10 |
| D | B | 2 | 5 | 14 |
| E | D | 3 | 3 | 3 |
| F | C | 6 | 8 | 10 |
| G | E, F | 1 | 1 | 1 |
| H | C | 6 | 10 | 14 |
| I | G, H | 3 | 4 | 5 |
What variance would be used in finding probabilities of finishing by a certain time?