Question: a. What is the make span? b. How much machine idle time is there? c. When is each job delivered compared with its due date?
a. What is the make span?
b. How much machine idle time is there?
c. When is each job delivered compared with its due date?
d. How much idle time (waiting time) is there for each job?
e. Devise a better job sequence for processing.
Step by Step Solution
3.58 Rating (162 Votes )
There are 3 Steps involved in it
a Makespan is 14 hours b Machine A has 5 units of idle t... View full answer