Question: As someone who has taken a project management course using this text and understands the need to select projects using a variety of factors, you
a. Use the information above and from question 3 to build a WSM, using a spreadsheet program such as Microsoft Excel. Make up your own scale to rate each project.
b. Graphically depict the final score for each project, using a bar chart.
c. If you can select only one project, which one should it be?
d. Does your choice change if the relative weights change to 10 percent, 10 percent, 30 percent, 30 percent, 10 percent, and 10 percent?