Question: At the site where the sample of Problem 8.18 was taken, the soil profile consists of about 6.5 m of sand and rubble fill and
At the site where the sample of Problem 8.18 was taken, the soil profile consists of about 6.5 m of sand and rubble fill and then 9.1 m of clay. The water table is about 1.8 m below the ground surface. Average densities of the sand and rubble fill are 1.45 Mg/m3 above the water table and 1.70 Mg/m3 below the water table. Estimate the consolidation settlement if the average stress increase in the compressible layer is:
(a) 50 kPa
(b) 100 kPa
(c) 250 kPa.
Step by Step Solution
3.47 Rating (157 Votes )
There are 3 Steps involved in it
a 50 kPa o 260 kPa from Problem 818 For the clay Psat Pary 1w 14... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1430-P-M-F-M(1978).docx
120 KBs Word File