Question: Calculate the takt time for a system where the total time per shift is 480 minutes, there is one shift, and workers are given two
Calculate the takt time for a system where the total time per shift is 480 minutes, there is one shift, and workers are given two 15-minute breaks and 45 minutes for lunch. Daily demand is 300 units.
Step by Step Solution
3.37 Rating (166 Votes )
There are 3 Steps involved in it
Demand 120 units per day 2 shifts of 480 ... View full answer