Question: Compute the takt time for a system where the total time per shift is 480 minutes, there is one shift, and workers are given two

Compute the takt time for a system where the total time per shift is 480 minutes, there is one shift, and workers are given two 15-minute breaks and 45 minutes for lunch. Daily demand is 300 units.