Claire received a new word-processing software program for her birthday. Sire also received a cheque with which
Question:
a. Arrange the activities into two logical sequences.
b. Construct a precedence network.
c. Determine the critical path by determining the length of each path. What is the expected duration of the project?
d. What are some possible reasons for tire project to take longer than expected?