Question: Complete the following problems: Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion (EAC).
Complete the following problems:
Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at completion (EAC). Please show calculations for all your answers
Planned value: 6700
Earned value: 6100
Actual costs: 7300
Budget at completion: 38900
Calculate the following values
CPI: _______________________
SPI: ____________________________
EAC: _____________________
Consider the following information:
PV=6500
EV=5000
AC=7200
BAC=32000
Expected Duration=12 weeks
Calculate the following values:
CV __________________
SV __________________
CPI __________________
SPI __________________
EAC __________________
Duration at Completion _______________
Please select the best answer from the following selection to complete each of the questions below related to task dependency.
Start -to-start
Finish-to-start
Start-to-finish
Finish-to-finish
.png)
Questions Filling in the name of the appropriate task dependency for each question Task A: Printout a series of computer images Task B: Photocopy the series of images Task A: Set up concrete foam foundation Task B: Pour the concrete Task A: Bake cupcakes Task B: Decorate cupcakes Task A: Paint the walls Task B: Pick out matching Carpet Task A: Completely test the product Task B: Complete the Product documentation
Step by Step Solution
3.37 Rating (163 Votes )
There are 3 Steps involved in it
Complete the following problems 1 Using the following information calculate the cost performance ind... View full answer