Question: project managment: Description: A small project was planned to be completed in 40 weeks, with a budget of $360,000, phased equally over the 40 weeks
project managment:
Description:
A small project was planned to be completed in 40 weeks, with a budget of $360,000, phased equally over the 40 weeks ($9,000 per week), with 2.5% of the work to be completed each week. At the end of the first 6 weeks, the project was 12% completed. The following is additional information related to this project:
Planned value (PV): $9,000 (each week)
Actual cost (AC): $60,000 (at the end of the first 6 weeks)
Budget at Completion (BAC) $360,000 (for the whole project)
Original Time Estimate (OTE): 40 weeks (for the whole project)
Required--Compute and answer the following (show all your calculations):
a) Rate of performance (RP):
b) Earned value (EV):c) i) Cost variance (CV):
ii) Schedule variance (SV):
iii) Cost performance index (CPI):
iv) Schedule performance index (SPI):d) Estimate at completion (EAC):
e) Estimate to complete (ETC)f) Estimated time to complete (ETTC):
g) How is work on the project progressing (be specific, indicating the underlined keyword):
i) Is it ahead of schedule or behind schedule? Why do you think so?
ii) Is it under budget or over budget? Why do you think so?
Notes:
You must show all your work that supports the answer
Identify the answer for each question with its letter code (eg. (a) or( ii)).