Question: Consider Table 6-2, Network Diagram Data for a Small Project. All duration estimates or estimated times are in days; and the network proceeds from Node

Consider Table 6-2, Network Diagram Data for a Small Project. All duration estimates or estimated times are in days; and the network proceeds from Node 1 to Node 9.


Consider Table 6-2, Network Diagram Data for a Small Project.


a. Draw an ADA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time.
b. Identify all of the paths on the network diagram and note how long they are, using figure as a guide for how to represent each path.
c. What is the critical path for this project and how long is it?
d. What is the shortest possible time it will take to complete thisproject?

ActivityInitial Node Final Node Estimated Duration 3

Step by Step Solution

3.43 Rating (159 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b Path 1 ABEHK Length 22222 10 days Path 2 ABEIJK Le... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

149-B-M-L-P-M (1223).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!