Question: Consider the following job information. Each job must proceed sequentially through the different work areas, and each area can work on only one job at
Consider the following job information. Each job must proceed sequentially through the different work areas, and each area can work on only one job at a time. Sequence the jobs according to the
(1) first come, first-served rule,
(2) Earliest due date, and
(3) Critical ratio.
Calculate the average lateness under each rule. Which rule performs best? Are any of the results completely satisfactory? What are the implications?
Estimated Days (TTT JOB PAINTING ASSEMBLY PACKING TOTAL TASK TIME DAYS UNTIL DUE A 1.5 2 0.5 4 15 B. 4 3 1 8 16 3 0.5 1 5.5 11 8 20
Step by Step Solution
3.48 Rating (165 Votes )
There are 3 Steps involved in it
tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGeneral textaligngeneral verticalalignbottom whitespacenowrap msorotate0 msobackgroundsourceauto msopatt... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
436-B-M-L-S-C-M (2815).xlsx
300 KBs Excel File