Question: Consider the following project network and activity times (in weeks): a. Identify the critical path. b. How much time will be needed to complete this
.png)
a. Identify the critical path.
b. How much time will be needed to complete this project?
c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?
d. Can activity C be delayed without delaying the entire project? If so, by how many weeks?
e. What is the schedule for activityE?
Finish Start ActivitvIA B C D E F G H Time 5 37 6 7 3 108
Step by Step Solution
3.52 Rating (166 Votes )
There are 3 Steps involved in it
a Critical path ADFH b 22 weeks c No it is a critical activity d Y... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
148-M-S-Q-M (36).docx
120 KBs Word File
