Question: The following project network and table provide the normal times and costs as well as the crash times and costs for the activities required to
-1.png)
-2.png)
Activity Normal Time, Weeks Cost $2,500 4,000 3,000 2,000 3,000 2,000 2,000 Crash Time. Weeks Cost $6,000 5,000 5,000 3,000 4,000 5,000 2,000 End Start
Step by Step Solution
3.42 Rating (177 Votes )
There are 3 Steps involved in it
Activity Normal Time wk Normal Cost Crash Time wk Crash Cost ... View full answer