Question: Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the
.png)
Activity Activity Predecessor Time (months) 3 4,5, 6
Step by Step Solution
3.42 Rating (155 Votes )
There are 3 Steps involved in it
Project completion time 23 weeks Activity Slack weeks 1 ... View full answer