Question: 3. Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate

 3. Construct a Gantt chart and project network for the following

3. Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path: Activity Activity Predecessor Time (months) 4 1 2 3 7 8 4 1 3 9 5 2 6 7 3 3 5 2 8 6 4,5,6 2 9 5