Question: Q 4 . [ Textbook Problem 8 - 3 ] Construct a Gantt chart and project network for the following set of activities, compute the

Q4.[Textbook Problem 8-3]
Construct a Gantt chart and project network for the following set of activities, compute the length of each path in the network, and indicate the critical path:
\table[[Activity,Activity Predecessor,Time (months)],[1,-,4],[2,-,7],[3,1,8],[4,1,3],[5,2,9],[6,3,5],[7,3,2],[8,4,5,6,6],[9,2,5]]