Question: Design and plot a critical ratio for a computer installation project that had planned constant, linear progress from 0 to an earned value of 200
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
Day Actual Planned CR 1 2 2 100 2 3 4 075 3 4 6 067 4 6 8 075 5 7 10 070 6 ... View full answer