Question: Industrial Building, Inc., has two project teams installing virtually identical, 4-story commercial buildings for a customer in two separate cities. Both projects have a planned
.png)
Compare the two projects in terms of general progress and according to criticalratios.
Team A: Team B: Earned Earned Day ValueVale A: Cost B: Cost 90 92 94 98 104 112 95 101 89 105 95 98 101 106 116 126 95 94 102 109 118