Question: During a violent thunderstorm with very high wind gusts in the third week of March, the broadcast tower for the public radio station, WVPR, atop
.png)
Using your best judgment, develop a CPM/PERT network for this project and determine the expected project completion time. Also determine the probability that the station signal will be back at full strength within threemonths.
Time Estimates (Weeks) Activity a Removal of debris b Survey new tower site c Procure structural steel d Procure electrical/ 12 15 18 30 32 broadcasting equipment e Grade tower site f Pour concrete footings f Pour concrete footings 0 18 22 gDeliver and unload steel3 broadcast equipment j Connect electrical cables 4 k Construct storm drains 0 and anchors h Deliver and unload electrical Erect tower 1 25 35 50 10 between tower and building 21 and tiles ackfill and grade tower site 4 6 10 m Clean up n Obtain inspection approval 1
Step by Step Solution
3.60 Rating (161 Votes )
There are 3 Steps involved in it
Activity Time ES EF LS LF Slack Variance a 817 0 817 ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
184_606c7f69a44f8_143867.xlsx
300 KBs Excel File
184-B-M-L-O-M (466).docx
120 KBs Word File