Question: The following CPM network has estimates of the normal time in weeks listed for the activities: a. Identify the critical path. b. What is the

The following CPM network has estimates of the normal time in weeks listed for the activities:

The following CPM network has estimates of the normal time

a. Identify the critical path.
b. What is the length of time to complete the project?
c. Which activities have slack, and how much?
d. Here is a table of normal and crash times and costs. Which activities would you shorten to cut two weeks from the schedule in a rational fashion? What would be the incremental cost? Is the critical pathchanged?

NORMAL TIME CRASH TIME NORMAL CRASH CosT ITY COST $7,000 5,000 9,000 3,000 2,000 4,000 5,000 $ 8,000 7,000 10,200 4,500 3,000 7,000 8,000

Step by Step Solution

3.50 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a ACDFG b 74545 25 weeks c B 2 weeks E 2 weeks d Activity Normal Time ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

287-B-M-L-S-C-M (1309).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!