Question: The following CPM network has estimates of the normal time in weeks listed for the activities: a. Identify the critical path. b. What is the
.png)
a. Identify the critical path.
b. What is the length of time to complete the project?
c. Which activities have slack, and how much?
d. Here is a table of normal and crash times and costs. Which activities would you shorten to cut two weeks from the schedule in a rational fashion? What would be the incremental cost? Is the critical pathchanged?
NORMAL TIME CRASH TIME NORMAL CRASH CosT ITY COST $7,000 5,000 9,000 3,000 2,000 4,000 5,000 $ 8,000 7,000 10,200 4,500 3,000 7,000 8,000
Step by Step Solution
3.50 Rating (170 Votes )
There are 3 Steps involved in it
a ACDFG b 74545 25 weeks c B 2 weeks E 2 weeks d Activity Normal Time ... View full answer