Question: During year 1, Meriwether Construction Company started a construction job with a contract price of $ 3,000,000. The job was completed in year 2 and

During year 1, Meriwether Construction Company started a construction job with a contract price of $ 3,000,000. The job was completed in year 2 and the company uses the percentage of completion method. The following information is available for year 1 and year 2:
During year 1, Meriwether Construction Company started a construction job

What amount of gross profit should Meriwether recognize for this job for year 2?
a. $ 250,000
b. $ 1,000,000
c. $ 350,000
d. $ 600,000

Year 1 Year 2 Cost incurred to date Estimated cost to complete Bilings to date Collections to date $ 500,000 $2,400,000 1,500,000 300,000 1,00.000 100,000 600,000

Step by Step Solution

3.45 Rating (174 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Choice c is correct The total cost for the contract was 2400000 The contract price ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

578-B-A-V-I (1552).docx

120 KBs Word File

Students Have Also Explored These Related Accounting Questions!