Question: Estimate the time it will take to complete the fourth unit of a 12-unit job involving a large assembly if the initial unit required approximately

Estimate the time it will take to complete the fourth unit of a 12-unit job involving a large assembly if the initial unit required approximately 80 hours for each of these learning percentages:
a. 72 percent
b. 87 percent
c. 95 percent

Step by Step Solution

3.34 Rating (163 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a 72 T n T 1 x Unit time ... View full answer