Question: Estimate the time it will take to complete the fourth unit of a 12-unit job involving a large assembly if the initial unit required approximately
Estimate the time it will take to complete the fourth unit of a 12-unit job involving a large assembly if the initial unit required approximately 80 hours, and the learning percentage is 72 percent