Question: For the network in Problem 9-4, determine the earliest start and finish times, latest start and finish times, and slack for each activity. Indicate how
Step by Step Solution
3.30 Rating (162 Votes )
There are 3 Steps involved in it
Activity Time ES EF LS LF Slack 1 7 0 7 2 9 2 2 10 0 10 0 10 0 3 6 ... View full answer