Question: Frames Ltd produces wooden window frames to order for the building industry. The size of frame depends on the specification in the contract. For the
The standard specification is as follows:
.png)
Fixed overhead is estimated at £160,000 per month for single-glazing and £100,000 per month for double-glazing. Estimated production per month for single-glazing is 4,000 units and for double-glazing is 2,000 units per month.
Required
Prepare a job cost estimate for a customer who intends to order 500 single-glazing and 200 double-glazing units?
Single-glazing Double-glazing Direct materials per unit labour per unit 6.5 hours at 5.00 per hour 8.0 hours at 5.00 per hour Variable production overhead charged at 6 per hour 130.00 90.00 32.50 40.00 48.00 39.00
Step by Step Solution
3.47 Rating (160 Votes )
There are 3 Steps involved in it
All the amounts are in Particulars Single glazing D... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
1372-B-M-A-M-A(3512).docx
120 KBs Word File