Question: Given the BOM and MPS for end items A and B, complete the MRP schedules for A, B, C, F and G. MPS 1 week

Given the BOM and MPS for end items A and B, complete the MRP schedules for A, B, C, F and G.
Given the BOM and MPS for end items A and

MPS

Given the BOM and MPS for end items A and

1 week 1 week c (4) 2 weeks 0 (2) 2 week8 G 4) 1 week t (2) weeks 1 week 2 w eek 1 week 1 week 1 week Item 5 7 8 200 250 300 100 100 100100100100

Step by Step Solution

3.47 Rating (170 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Item A B C F G Lot Size Rule L4L L4L Multiples FOQ 500 Multiples FOQ 1000 Multiples FOQ 1000 Safety ... View full answer