Question: Given the data in Problem 7, determine the first activities to be crashed by the following priority rules: (a) Shortest task first. (b) Most resources
(a) Shortest task first.
(b) Most resources first (use normal cost as the basis).
(c) Minimum slack first.
(d) Most critical followers.
(e) Most successors.
Step by Step Solution
3.40 Rating (172 Votes )
There are 3 Steps involved in it
In all cases crashing is applied only to critical path activiti... View full answer