Question: Consider the project network below. Suppose the duration of both activities A and D can be reduced to one day, at a cost of $15
Consider the project network below. Suppose the duration of both activities A and D can be reduced to one day, at a cost of $15 per day of reduction. Also, activities E, G, and H can be reduced in duration by one day at a cost of $25 per day of reduction. What is the least-cost approach to crash the project two days? What is the shortest crashed duration, the new critical path, and the cost ofcrashing?
.png)
C1 12 A4 D5G3 End Start H5 Ul Fl
Step by Step Solution
3.47 Rating (157 Votes )
There are 3 Steps involved in it
Activity Normal Time Crash Time Time Slope A 4 1 3 15 B 3 3 0 C 1 ... View full answer