Question: Given the following data on inputs and outputs at a work center, determine the cumulative deviation and the backlog for each time period. The beginning
.png)
PERIOD Input Planned2 Actua2 200 200180 190 190 200 210 200179 195 193 194 PERIOD Outpu Plnd 200 200 10190190200 205 194 177 195 193 200
Step by Step Solution
3.47 Rating (163 Votes )
There are 3 Steps involved in it
Determine the cumulative deviation and the backlog for each period Devi... View full answer