Question: Here is a CPM network with activity times in weeks: a. Determine the critical path. b. How many weeks will the project take to complete?
Here is a CPM network with activity times in weeks:
.png)
a. Determine the critical path.
b. How many weeks will the project take to complete?
c. Suppose F could be shortened by two weeks and B by one week. How would this affect the completiondate?
A(7) G(3) D(6) E(4) F8)
Step by Step Solution
3.65 Rating (178 Votes )
There are 3 Steps involved in it
a AEGCD b 26 weeks c No difference in ... View full answer