Question: Given the following production schedule, compute the available-to-promisequantities. WEEK 4 Model A MPS BI 60 20 30 202020 50 0 20 Commited Customer Orders 50
Given the following production schedule, compute the available-to-promisequantities.
.png)
WEEK 4 Model A MPS BI 60 20 30 202020 50 0 20 Commited Customer Orders 50 ATP:D 310 20 20 10 0