Question: Given the information in the following table: a. Construct the network diagram. b. Find each activitys ES, EF, LS, and LF. c. Identify all paths.
Given the information in the following table:
.png)
a. Construct the network diagram.
b. Find each activity’s ES, EF, LS, and LF.
c. Identify all paths. Which path is the critical path?
d. Calculate the slack for each activity.
e. How long will it take to complete the project?
Activity Duration Predecessor None b, d
Step by Step Solution
3.30 Rating (162 Votes )
There are 3 Steps involved in it
a Network diagram b Each activitys ES EF LS and LF See following spre... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
132-B-M-L-P-M (1040).docx
120 KBs Word File