Question: Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial
Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish (e.g., trial and error), develop a loading chart for resources, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exists. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now? Could something like this happen in realprojects?
.png)
0 1 ME 0 2 ME ME Develop a loading schedule for each resource below. (Figure 8.3) ME 2 3 56 7 8 10 11 12 Fill in the times below for a resource activity schedule. ID/RES ES LS EF LF SL 1-EE 2-EE 3-ME 4-EE 5-ME 6-ME 7-EE ES ID EF SL LS SL
Step by Step Solution
3.33 Rating (168 Votes )
There are 3 Steps involved in it
Instead of taking 9 days the duration has been extended to 11 days and all ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
177-B-M-L-P-M (1391).docx
120 KBs Word File