Question: Given the time-phased work packages, complete the baseline budget for the project. Time-phased budget ($ 000) Week Task Budget Week 1 Week 2 Week 3

Given the time-phased work packages, complete the baseline budget for the project. Time-phased budget ($ 000) Week Task Budget Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 8 8 19 6 5 8 26 5 8 5 8 Activity 1 Activity 2 Activity 3 Activity 4 Activity 5 Total 18 6 6 6 16 9 7 87 Cumulative