Question: Houston Milling is a subcontractor to Pratt & Whitney, which makes jet engines. Houston Milling makes two different fuel pump housings for two Pratt &
These are performed in two separate machining departments (Department 1 and Department 2). Both housings, A11 and D43, require machining in both Departments 1 and 2. Before the parts are machined, the machines must first be set up, which includes cleaning the machine, checking the tools in the machine, adjusting the tolerances, and then finally machining some trial parts. Houstons current accounting system tracks the number of setups and direct labor hours used by each part. Table 1 summarizes the indirect costs of producing A11 and D43. (The direct costs such as direct labor and materials are ignored to simplify the computations.)
Setup and machine hours in the two departments are pooled into two cost pools: setup and machining. Table 1 allocates the costs in these two pools to the two products. Under this accounting system, A11 has indirect costs of $ 8,600 and D43 has indirect costs of $ 6,400. Management believes that the current accounting system is not producing accurate costs for the two products because the two cost pools are too aggregated. They decide to disaggregate the data and use four cost pools. They collect some additional data, which are summarized in Table 2.
Required:
a. Calculate revised cost allocations based on the disaggregated data in Table 2. Number of setups is used to allocate the indirect cost of setups in both Departments 1 and 2 and direct labor hours are used to allocate the machining costs in Departments 1 and 2.
b. Prepare a short memo describing the pros and cons of the revised allocated indirect costs in (a) compared to those in Table 1.
Continue
-1.png)
-2.png)
c. After completing the analysis in (a) and (b), some additional data are collected from a special study of setup hours and machine hours in the two departments. These data are presented in Table 3. In particular, setup hours and machine hours are collected in the two departments. Management now believes that setup hours and machine hours more accurately reflect the true cause- and- effect relations of setup costs and machining costs in Departments 1 and 2 than number of setups and direct labor hours, respectively.
Based on the data presented in Table 3, calculate revised cost allocations for A11 and D43. Setup costs in Departments 1 and 2 are to be allocated based on setup hours, and machining costs in Departments 1 and 2 are to be allocated based on machine hours.
d. Compare the total product costs for A11 and D43 in Table 1 and parts (a) and ( c ). What conclusions can youdraw?
TABLE1 Houston Milling Allocated Indireet Costs of Producing Parts A1l and D43 Functions Setup Machining Total $5,000 Number of setups 10 15 25 $200/setup $2,000 3,000 $10,000 Direct labor hours Indirect cost $15,000 Allocation base Usage: All D43 34 100 $100/DL hr S 6,600 Total Allocation rate Allocations: A11 D43 Total $ 8,600 6.400 $15,000 3,400 $5,000 10,000 TABLE 2 Houston Milling Disaggregated Cost Pool Data Setup Machining Department I Department 2 Department I Department 2 Total Total cost Allocation base $3,000 Number of setups $2,000 Number of $8,000 $2,000 $15.000 labor hours 32 18 50 labor hours 34 16 50 Usage: All D43 Total 13 20 TABLE3 Houston Milling Setup Hours and Machine Hours in Departments 1 and 2 Department 1 Department 2 Setup Machining Machining Total cost Allocation base Usage: All $3,000 Setup hours 15 15 Setup $2,000 Setup hours $2000 Machine hours 120 Machine hours 115 85 200 D43 Total 30 10 200
Step by Step Solution
3.38 Rating (170 Votes )
There are 3 Steps involved in it
a The table below calculates product costs using the more disaggregate data Houston Milling Revised Cost Allocations Based on Disaggregated Cost Pool ... View full answer