If desired output is 75 units per hour, compute (a) The associated cycle time, (b) The assignment

Question:

If desired output is 75 units per hour, compute
(a) The associated cycle time,
(b) The assignment of tasks to stations using the longest task time rule, and
(c) The efficiency of your solution