Question: A dress-making operation is being designed as an assembly line. Table shows the tasks that need to be performed, their task times, and preceding tasks.

A dress-making operation is being designed as an assembly line. Table shows the tasks that need to be performed, their task times, and preceding tasks. If the goal is to produce 30 dresses per hour, answer the questions that follow the table.


A dress-making operation is being designed as an assembly line.


(a) Compute the cycle time.
(b) Which task is the bottleneck?
(c) What is the maximum output for this line?
(d) Compute the theoretical minimum number of stations.
(e) Assign work elements to stations, using the longest task time rule.
(f) Compute the efficiency and balance delay of yourassignment.

Table Dress-Making Task Information Immediate Predecessor None None None Work Element A. Cut dress body B. Cut sleeves C. Cut collar D. Sew dress body E. Sew sleeves to dress F Sew collar to dress G. Hem dress H. Package dress Task Time sec 30 40 20 100 25 50 50 90 B, D C, D D, E, F

Step by Step Solution

3.49 Rating (162 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a C 3600 secondshour30 unitshour 120 secondsdress b Task D c Max... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

194-B-M-L-O-M (657).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!