In a construction company, project completion time is considered to be normally distributed with mean completion time

Question:

In a construction company, project completion time is considered to be normally distributed with mean completion time being 16 weeks. There is an 80% probability that a project will take between 14 to 18 weeks to reach completion. What is the variance of project completion time?