Question: In a continuous-review inventory system, the lead time for custom six-panel doors is five weeks. The standard deviation of demand during the lead time is

In a continuous-review inventory system, the lead time for custom six-panel doors is five weeks. The standard deviation of demand during the lead time is 50 doors. The desired cycle-service level is 99 percent. The supplier of the custom doors decided for competitive reasons to now quote a one-week lead time. How much can safety stock be reduced without reducing the 99-percent cycle service level?
Definition: Cycle-service level = the probability of not stocking out.
a. At lead time of 5 weeks
b. At lead time of 1 weeks

Step by Step Solution

3.25 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a b Thus by reducing the lead ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

852-B-M-L-S-C-M (4438).docx

120 KBs Word File

Students Have Also Explored These Related Management Leadership Questions!